Lyondell Basell, power plant Wesseling

Air preheater boiler 4

Type: CXS 24 / 2.250

 

  • Execution of revision works
  • Inspection of rotor bearings
  • Retrofit of radial and circumference sealing leaves
  • Rehabilitation of soot blowers, adjustment of blowers
  • Rehabilitation of compensator protection plates
  • Rehabilitation of radial walls, cold end
  • Dismantling and reassembly of cold end layer
  • Retrofit of rotor flange segments, cold end
  • Execution period:  May / June 2016